12. Slide Gates

140

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

Slide Gates at Base of Dryer (For Emergency Grain Discharge)

1. After outside bottom wall sheets (20" solid with cut outs) are installed at base of dryer, install slide

gates as in

Page 139

.

(See Figure 12B and

Figure 12C.)

2. After outside hopper panels with cut outs are installed, install slide gates as in

Page 139

.

(See Figure 12D and

Figure 12E.)

Figure 12B Installing slide gate plate to

frame on outside bottom wall sheet and mid way

sheet. (For emergency discharge and cleaning.)

Figure 12C Slide gate installed to outside bottom wall

sheet. (For emergency discharge.)

Figure 12D Installing slide gate plate to frame on

outside hopper panels. (For emergency discharge.)

Figure 12E Use 5/16" x 3/4" galvanized at hopper

clean outs. Slide gate installed to outside hopper

panels. (For emergency discharge.)