Fuel piping, Chapter 23 fuel piping, Fuel piping (main) (natural gas or liquid propane) – Grain Systems PNEG-707GSI User Manual

Page 238

Advertising
background image

238

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

23. Fuel Piping

See Orientation Section on Page 19

for dryer dimensions, components, wall sheet guidelines, etc.

See Appendix A on Page 435

for tools and equipment,

Appendix B on Page 437

for hardware, etc.

Fuel Piping (Main) (Natural Gas or Liquid Propane)

Piping through Housing

Attach 12" nipple and union to burner manifold. Run first 3" pipe section vertically down through reducer
housing and out pre-cut hole in center of fan housing splice. Secure with pipe riser clamp.

Piping in Cool Section

Continue 3" fuel piping vertically into cool section of dryer to just below bottom of fans. Add 90° elbow
and continue piping horizontally through dryer window. Secure fuel piping with clevis hanger and
threaded rod as needed.

Piping through Window

Run 3" fuel piping out dryer window and add elbow.

Piping Outside Dryer

Continue 3" fuel piping from dryer window vertically down, parallel to side of dryer. Secure to
compression angle with U-bolt. Add union and 12" nipple before attaching fuel train.

NOTE:

See Page 244

for fuel train.

Fuel piping runs from bottom of burner to fuel train on foundation.

(Main) Fuel piping and pilot fuel piping usually run parallel.

Electricians will install pilot fuel piping. Pilot fuel piping (3/8" copper tubing) runs from pilot section on
burner to pilot section on fuel train.

Figure 23A 3" Fuel Piping

Important Safety Precautions:
Dryer has sharp edges. These sharp edges may cause serious injury.
Use appropriate personal protective equipment. Use proper lifting techniques.