21. Hopper

226

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

Hopper (Cross Section) Example - All Models (Continued)

Figure 21Q While installing outside hopper panels,

allow ends to overlap at center of dryer.

Figure 21R Close Up - Bolting outside hopper

panels (R.H./L.H.). Lap outside hopper panels-R.H.

with cut out (arrow) on outside of dryer so slide

gate will slide freely.

A. Bolt flat edges together.

B. Angled edges will bolt together later, under

hopper channel with common bolt.

Figure 21S Installing outside hopper panels.

Figure 21T Bring metering drum floor into outside

hopper before closing in with last panel.

Figure 21U

IMPORTANT: After all outside hopper panels are in

place, secure against wind with
temporary bolts, especially overnight.

Figure 21V Aligning outside hopper panels before

installing hopper discharge weldment.