19. Tower Base

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

211

Upper Legs

See Figure 19A on Page 204 and

Figure 19B on Page 205

for placement of upper legs. Install upper legs

with support clip side to inside of dryer.

Outside dryer - Bolt upper leg through compression angle weldment to base stiffener weldment.

(See Figure 19S on Page 212.)

Use 5/8" x 2-3/4" grade 8 bolts and nuts.

Inside dryer - Bolt support clip on upper leg to compression angle weldment.

(See Figure 19T on Page 212.)

Use 5/8" x 1-1/2" grade 8 bolts and nuts.

Figure 19P

Figure 19Q Aligning upper leg to

base stiffener weldment.

Figure 19R Placing upper leg directly

under base stiffener weldment.

Lower leg

Upper leg