Rolled plenum channels – Grain Systems PNEG-707GSI User Manual

Page 54

Advertising
background image

5. Plenum Roof

54

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

Figure 5N

Figure 5O

Rolled Plenum Channels

Install 1 ring of rolled plenum channels to reinforce the ring of inside top wall sheets as follows.

1. Bolt one (1) plenum channel splice to each rolled plenum channel with 5/16" x 1" whiz bolt and nut

before installing to dryer.

Figure 5P Plenum Channel Splice

Figure 5Q Plenum Channel Splices - as shipped.

Throughout Dryer

Install rings of rolled plenum channels to wall sheets so closely that fingers will not fit between them.

2. Snug bolt rolled plenum channels to inside top wall sheets with 5/16" x 3/4" whiz lock bolts and nuts.

NOTE: Bolt in fifth bolt hole from bottom of vertical channel.

If necessary to fit last rolled plenum channel into ring, remove bolts from wall sheets

on both sides, pull one (1) bolt out of vertical channel (above or below), bend and push it
down into place. (Do not cut it.)