6. Tower Roof

70

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

See Orientation Section on Page 19

for dryer dimensions, components, wall sheet guidelines, etc.

See Appendix A on Page 435

for tools and equipment,

Appendix B on Page 437

for hardware, etc.

Steps to Construct Tower Roof

Roof Band

Use 5/16" x 3/4" stainless steel whiz lock bolts and 5/16" nuts. (Galvanized can be substituted here.)

Install roof band sections so they overlap around outside of dryer. Bolt each roof band section across
three (3) vertical channels, in top two (2) bolt holes of each vertical channel.

Figure 6D Roof band section. Top of roof band has pairs of

bolt holes alternating with single bolt holes. Bottom of

roof band has evenly spaced bolt holes.

Figure 6E Installing roof band sections to overlap

around (outside) top of vertical channels.

Important Safety Precautions:
Dryer has sharp edges. These sharp edges may cause serious injury. Use
appropriate personal protective equipment. Use proper lifting techniques.

Top