Assembly

Slide rail and support rail (continued)

Method 1: Using aluminium rivets

Mounting:

Rivet crimping pliers/rivet crimping clamp

Aluminium rivets

1

Insert rivets in the holes, using rivet crimping pliers or
a rivet crimping clamp. For type of rivet, see table on
previous page.

2

If working space is limited, the rivet crimping clamp
might be easier to use. The two crimping tools per-
form the same task, but the pliers are more efficient
and easier to use.

3

Check that the rivets do not protrude over the surface
of the slide rail.

Check both top and underneath surface of slide rail for
protruding metal.

4

Keep a distance of approximately 30 mm between riv-
ets and idler unit. This is in case the idler unit has to
be removed after conveyor system assembly.

correct

wrong