background image

4.1 Start Up

66

YASKAWA TM.iQp.01 iQpump Drive User Manual

4.1

Start Up

In order to provide the most reliable iQpump drive available and to avoid any extra costs related to loss or reduction of warranty

coverage, an authorized Yaskawa service representative should complete this start up procedure. Please complete the following checklist

and maintain it in a secure location as technical service personnel may request information from this checklist.

Drive Start Up Preparation

Date:____________________________________________

Start Up Person:

Company Name:_________________________________

Start Up Location: _________________________________

Sales Order #: ___________________________________

Serial #: _________________________________________

Printed Name: ___________________________________

Drive Location: ___________________________________

Phone #: _______________________________________

Signature: _______________________________________

Owners Representative:

Printed Name: ___________________________________

Phone #: _________________________________________

Company: ______________________________________

Signature: ________________________________________

Step

…

1. The iQpump drive is thoroughly tested at the factory. The start up person should verify that the iQpump drive is free of shipping

and installation damage. Shipping damage is not covered by the Yaskawa warranty. Claims must be filed with the shipping

company as soon as possible for any potential recovery via insurance.

…

2. Review the iQpump (P7U) User Manual (TM.iQp.01) shipped with the iQpump drive.

…

3. Verify that the model number and voltage ratings in the purchase order match the nameplate data for each unit.

…

4. Location of the iQpump drive is important to achieve proper performance and normal operating life. The unit should be installed

in an area where it is protected from:

ƒDirect sunlight, rain or moisture

ƒCorrosive gases or liquids

ƒVibration, airborne dust or metallic particles

…

5. Ensure the iQpump drive is on a vertical surface with adequate space for air circulation (4.75” above and below, 1.2” on each

side). Refer to Figure 1.5.

…

6. Verify that the proper branch circuit protection is installed in front of the iQpump drive. Refer to Appendix E Peripheral

Devices for proper input fuse or circuit breaker sizing.

…

7. Avoid running input and output wiring in the same conduit.

…

8. Avoid routing power wiring near equipment sensitive to electrical noise.