Applying power, Start-up status indications – Rockwell Automation 20G PowerFlex 755 Drive Embedded EtherNet/IP Adapter User Manual
Page 21

Rockwell Automation Publication 750COM-UM001E-EN-P - October 2013
21
Installing the Adapter
Chapter 2
Applying Power
Install the drive cover, and apply power to the drive. The embedded EtherNet/IP
adapter receives its power from the drive. When you apply power to the
embedded EtherNet/IP adapter for the first time, its ENET status indicator
should be steady green or flashing green after an initialization. If it is red, there is
a problem. See
Start-Up Status Indications
After power has been applied, the drive STS (status) indicator and the embedded
EtherNet/IP adapter ENET and LINK status indicators can be viewed on the front
of the drive (
Figure 3
). Possible start-up status indications are shown in
Table 1
.
Figure 3 - Drive and Adapter Status Indicators
ATTENTION: Risk of equipment damage, injury, or death exists. Unpredictable
operation may occur if you fail to verify that parameter settings are compatible
with your application. Verify that settings are compatible with your application
before applying power to the drive.
➊
➋
➌