Chapter 12 Installing, Removing, and Replacing

Cabling the Library

Dell PowerVault ML6000 User’s Guide

232

Required tools:

None

1

If your library is larger than 14U, install it in a rack. See

Installing the

Library in a Rack

on page 333 for instructions. The instructions

include procedures for removing and replacing tape drives.

2

For each FC I/O blade installed in a 9U Library Expansion Module,

connect the 9U Library Expansion Module containing the FC I/O

blade(s) to a port in the Ethernet hub on the LCB:

a

If the FC I/O blade is installed in the bottom bay of the 9U

Library Expansion Module, connect one end of an Ethernet cable

to the Ethernet port labeled

LOWER

in the lower right corner of

the 9U Library Expansion Module. Connect the other end of the

cable to a port in the Ethernet hub on the LCB.

b

If the FC I/O blade is installed in the upper bay of the 9U Library

Expansion Module, connect one end of an Ethernet cable to the

Ethernet port labeled

UPPER

in the lower right corner of the 9U

Library Expansion Module. Connect the other end of the cable to

a port in the Ethernet hub on the LCB.

c

Follow the instructions in

Cable Management Guidelines

on

page 237 for best practices in routing the Ethernet cables.

Warning:

All libraries taller than 14U must be installed in a rack

having a main protective earthing (grounding) terminal,

and power must be supplied via an industrial plug and

socket-outlet and/or an appliance coupler complying with

IEC 60309 (or an equivalent national standard) and having

a protective earth (ground) conductor with a cross

sectional area of at least 1.5 mm

2

(14 AWG).

To ensure proper airflow and access space, Allow 60 cm

(24 inches) in the front and back of the library.

Note:

Pay attention to where the operator panel is positioned in the

rack for optimum usability.

Note:

Without these Ethernet cables connected, the FC I/O

blades will not work.