Acquisition Modules and Platinum Firmware

Networking Configuration

User description: If you are configuring a number of watchdogs give each of

them memorable names.

Enable: Should normally be ticked but can be left clear if you only want to
use the associated PPP connection occasionally.

Delete: Deletes the instance when the form is submitted.

Daemon startup delay: If the PPP connection relies on a modem link for its

transport, there may be a significant delay between instructing the PPP link to
start and the connection being established. So that the watchdog does not

falsely detect a failed link during this period, it can be instructed to sit idle for
a number of seconds before it begins to test the link. The length of the

required delay should be entered into the field.

Test command: Once the start-up delay time has elapsed, the watchdog
periodically tests the connection. To ensure that there is a valid end-to-end

connection where, for example, a multi-hop link is in use, the exact method of
testing is user-configurable: any valid command can be entered into the field

and its exit status is taken to represent the link status (zero for link up,
non-zero for down). The most common method used is to use the ping

command to verify ICMP connectivity to the ultimate remote host, but you are
free to use the command or script of your choice here, so long as it returns a

non-zero exit status on link failure.

Time between tests: Determines how often the configured test is applied. It
can be set high to conserve bandwidth or set low to improve failure response

times. It can also be used to keep a sparsely-used link alive where a
“disconnect-on-inactivity” feature would otherwise interrupt it.