4-7

Use urethane foam to seal the space between the conduit

and the corbel or manhole wall to prevent infiltration into

the manhole.

Running the cable and conduit from the manhole to the EMU location

7. Provide enough slack in the cable at the manhole end to allow

removal of the monitor from the manhole during service

activities.

Note:

Do not connect the communication cable to the

monitor at this time!

8. Provide approximately 40 (102 cm) inches of excess cabling at

the designated EMU location.

9. (applies only to applications requiring conduit) Use urethane

foam or a sealing fitting to form a seal between the

communication cable and conduit at each end of the conduit.

This will prevent sewer gases from entering the EMU

enclosure, moisture from entering the conduit during a

surcharge, and inflow from entering the manhole.