Replacing the battery in the emu, Replacing the emu modem – ADS Environmental Services FlowShark QR 775003 A2 User Manual

Page 200

Advertising
background image

Maintenance and Troubleshooting 8-15

5. Once maintenance is complete, re-mount and secure the EMU

to the panel inside the enclosure using the fasteners.

6. Replace or close the cover to the enclosure.

Replacing the Battery in the EMU

If the Monitor Status report from Profile reveals an external voltage

of 8.0 volts or less, replace the battery pack in the EMU. The EMU

uses one non-IS battery pack (ADS p/n 5000-0557).
Replace the battery pack in the following way:
1. Disconnect the battery cable from the EMU power cable, and

remove the battery pack from the EMU.

2. Install the new battery with the cable extending out the left side

of the compartment.

3. Connect the cable from the new battery pack to the EMU

power cable.

4. Have a data analyst contact the monitor remotely to verify

communication and the external battery voltage.

5. Replace the cover on the EMU and tighten the four plastic

screws, provided all EMU maintenance is complete.

Replacing the EMU Modem

Replace the quad-band GSM/GPRS wireless modem (ADS p/n

507209) in the EMU in the following way:
1. Disconnect the power (battery or external) running to the

EMU/modem.

2. Remove the two Phillips head screws that secure the modem

bracket to the back panel of the EMU, and then remove the

3. Disconnect the antenna cable from the modem by unscrewing

the gold nut (at the connector end of the antenna cable) from

the modem connector.

4. Remove the modem bracket with the modem from the EMU.

Advertising