ADS Environmental Services FlowShark QR 775003 A2 User Manual

Page 185

Advertising
background image

Monitor Installation

7-9

Positioning the nuts on the stud to receive the mounting bracket

11. Mount the bottom of the mounting bracket onto the monitor

flange with two 3/8-inch x 1-inch hex bolts, 3/8 – 16 nex nuts,

and 3/8-inch washers. It may be necessary to drill new holes in

the flange.

12. Carefully lower the monitor into the manhole, and place the

keyhole in the bracket over the outer nut on the stud.

Note:

ADS strongly recommends attaching a security line

to the monitor before lowering it into the manhole to avoid

accidentally dropping the monitor down into the manhole

during installation.

13. Slide the bracket against the inner nut and washer, and tighten

and secure the outer nut against the bracket.

14. Neatly coil and secure the excess sensor and communication

cables in the manhole to simplify future monitor service

activities. Secure the cables to plastic anchors or ¼-inch x 2¼-

inch anchor bolts using 14-inch cable ties.

Note:

Be careful to avoid damaging the sensor cables

during installation activities. Even small pinholes in the

cable can cause a sensor to malfunction or fail.

Advertising