5–3

Perform the Production Diagnostic Tests

Set Up the Board

4.

Install six short SMA cables to the DPA SMA connectors:

Connect DPA_CLKOUT (P & N) to DPA_CLKIN

Connect DPA_TX0 (P & N) to DPA_RX0

Connect DPA_TX1 (P & N) to DPA_RX1

See Figure 5–3.

1

Take care to connect the cables to the proper connectors and
ensure that the cables are completely seated.

Figure 5–3. Connect the Short SMA Cables for the SS DPA test

5.

Install eight SMA cables to the transceiver SMA connectors as
shown in Figures 5–4 and 5–5. Do not overtighten the connectors
(using your fingers is good enough). Connect TX_P[3:0] to
RX_P[3:0] and TX_N[3:0] to RX_N[3:0].

1

Take care to connect the cables to the proper connectors
(there are 2 sets of connectors, 8 vertical launch and 8 edge
launch). Channels 0 and 1 are the edge launch and Channels
2 and 3 are the vertical launch connectors.