11. Maintenance and Inspection

77

11. Maintenance and Inspection

11.1 Inspection Items and Schedule

Perform maintenance work according to the schedule below.

The schedule is set assuming eight hours of operation a day. When the operation time is long such as 24-hour

operation, shorten the maintenance intervals as needed.

Visual inspection Check interior

Grease supply

*2

Start of operation

After 1 month of operation

After 6 months of operation

*1

After 1 year of operation

Every 6 months thereafter

Every 1 year

*1 If grease is found degraded as a result of interior check, add grease.

*2 If continuous back-and-forth operations are performed over a distance of 30 mm or less, grease film may be

broken. As a guide, operate the actuator back and forth five times or so over a distance of

50 mm or more after every 5,000 to 10,000 cycles.

11.2 Visual Inspection of the Machine Exterior

Check the following items when carrying out visual inspection.

Body

Loose mounting bolts?

Cables

Damage to cables or connection to connector box?

Stainless sheet

Damage, foreign deposit or slacks?

General

Unusual noise or vibrations?

• If the stainless sheet is slacked, make adjustment as deemed necessary to remove the slacks.

• As a rough guide, the stainless sheet will last for 5,000 km of traveled distance.

However, the stainless sheet should be replaced earlier depending on the condition of use.

The stainless sheet must be replaced at an IAI site (the actuator must be brought to IAI) or at the customer’s

site by IAI’s service personnel, as a rule.

• If the actuator is fixed vertically, grease applied to the guide may drip depending on the environment. If this

happens, clean and add grease as necessary.