SECTION 4 - BOOM & PLATFORM

3121262

– JLG Lift –

4-81

6. Using tool JLG p/n 4120043, torque the Outer Mid

Boom Retract Adjustment Nuts to 80 ft-lb (108 Nm),
alternating between the two ropes until both main-
tain the required torque.

7. Using tool JLG p/n 4120043, torque the Fly Boom

Retract Adjuster Nuts to 80 ft-lb (108 Nm), alternat-
ing between the two ropes until both maintain the
required torque.

8. Retract the boom 2-3 feet (0.6-1.0 m). Do not fully

retract or bottom out the booms.

9. Using tool JLG p/n 4120043, torque the Outer Mid

Boom Extend Adjustment Nuts to 80 ft-lb (108 New-
ton meters), alternating between the two ropes until
both maintain the required torque.

10. Using tool JLG p/n 4120040, torque the Fly Extend

Adjustment Nuts to 10 ft-lb (13.5 Nm), starting with
the inside ropes and doing the outside ropes last.
Refer to Figure 4-21., Torque Sequence for Fly
Extend Rope.
Alternate between the four ropes until
all maintain the required torque.

Outer Mid Retract Adjusting

Nuts and Lock Plates

Fly Boom Retract Adjusting

Nuts and Lock Plates

Outer Mid Extend Adjusting

Nuts and Lock Plates

Fly Boom Extend Adjusting

Nuts and Lock Plates

3 1 2 4

Figure 4-21. Torque Sequence for Fly Extend Rope