JLG 1500SJ Service Manual User Manual

Page 294

Advertising
background image

SECTION 4 - BOOM & PLATFORM

4-48

– JLG Lift –

3121262

34. Apply JLG Threadlocker P/N 0100019 to the bolts

and attach the cable guide to the inner mid boom
section with the mounting hardware. Torque the
bolts to 165 ft.lbs. (224 Nm).

35. Push the cylinder the rest of the way into the inner

mid boom assembly.

36. Install the cylinder trunnion blocks and shims.

37. Using Super Lube®, lubricate all wear surfaces on

the inside of the boom base section and the outside
of the inner mid boom section.

38. Insert the inner mid boom section part way into the

boom base section enough to be able to pull the
outer mid retract cables out through the hole at the
bottom front of the boom base section.

39. Apply JLG Threadlocker P/N 0100011 to the bolts

and install the front lower wear pads into the boom
base section. Torque the bolts to 50 ft.lbs. (68 Nm).

Advertising