Commissioning Procedure
Preliminary Setup
A.
Ensure the work area is clean and tidy. Pathways to main disconnect and
emergency stop push button must be clear and unobstructed.
B.
The following test equipment is to be prepared for use:
•
Test power supply, supplied with each controller
•
Multimeters
•
Hi-Pot Tester (recommended) or Megger
•
Oscilloscope with memory (optional)
C.
Complete drawing package and parts list.
D.
Specification of project.