IMPORTANT COMMISSIONING CHECKS

Inspect the equipment for any signs of physical damage.

Verify SMC Flex physical installation is complete.

Verify the integrity and operation of all safety interlocks.

Verify that motor mechanical installation is complete.

Verify that Incoming Power wiring to SMC Flex is complete and all
connections are tight.

Verify that Motor cabling to SMC Flex is complete and that all
connections are tight.

Verify that Control wiring to SMC Flex is complete.

Check for any damaged components and verify that electrical clearances
have not been reduced while installing power cables.

Verify Incoming Power System Grounding
(Floating/Solid-Ground/Resistive Ground) and determine if Vcom on the
interface board should be connected to a ground reference or not (refer
to

Resistance Checks on page 68

).

Check if there are any Power Factor Correction Capacitors (refer to

Power

Factor Correction Capacitors on page 51 of Chapter 2

for correct

installation requirements of these capacitors).

Check if Surge Capacitors and/or Surge Arrestors are installed at the
motor. Open motor junction box and verify it by yourself. These must be
disconnected from the circuit. (refer to

Surge Arrestor Protection Devices

on page 52 of Chapter 2

).

Verify fiber-optic cables are connected at the right location (FO cables on
Phase-A power pole go to Phase-A on the Interface board, Phase-B of
power pole to Phase-B on the Interface board and Phase-C of power pole
to Phase-C on the interface board) and the connectors are fully seated in
their sockets.

Verify that circuit board plug connectors are installed and fully inserted in
their sockets.

Verify that the cooling fan (if supplied) is secured and the rotor is not
obstructed.

Complete device resistance checks per user manual (refer to

Resistance

Checks on page 68 of Chapter 3

).

ATTENTION: When commissioning a MV SMC Flex, it is critical that following
important checks are completed. For more details, follow the commissioning
guidelines that follow this page.