Inspection and Unpacking

Liebert

®

CRV

10

3.3

Moving the Unit Using Rigging

1. Use a pallet jack or forklift to raise the packaged unit.
2. Place slings under the skid runners, equally spacing the slings to make sure the unit is balanced

(see Figure 9).

3. Lower the unit and remove the pallet jack or forklift.
4. Connect the slings to the lifting device, using spreader bars or similar equipment to protect the

unit (see Figure 9).

5. Move the unit to its installation location. Two or more properly trained and qualified personnel

are required to move the Liebert CRV to its installation location.

6. Lower the Liebert CRV and remove the slings.

Figure 9

Moving the unit using rigging

3.4

Unpacking the Liebert CRV

1. Remove the lag bolts securing ramp to skid.
2. Place the ramp and and the plastic bag with orange clips to the side for use in removing the unit

from the skid.

3. Remove the stretch film and corner/side packaging planks from around the unit.
4. Remove the unit bag when ready to install the unit.

!

CAUTION

Risk of sharp edges, splinters and exposed fasteners. Can cause personal injury.
Only properly trained and qualified personnel wearing appropriate safety headgear, gloves,

shoes and glasses should attempt to move, lift or remove packaging from the Liebert CRV or

prepare the unit for installation.

NOTE
Wrapping one or two more straps around the middle of the Liebert CRV will improve stability

when it is lifted.