7. Preparations for commissioning

Festo.P.BE-CMMS-ST-G2-HW-EN 1008NH

119

7.7

Timing diagram switch-on sequence

Power On

DOUT3: #ERROR

Controller release

Output stage

switched on

Holding brake

released

Speed Setpoint

Speed actual

value

t1

t2

t3

t4

a / b

Output stage

release

t2

DOUT0: READY

t1

approx. 500 ms Execution of boot program and application start

t2

> 1.6 ms

t3

= 10 ms

Depends on the operating mode and the state of the drive

t4a

= N x 1.6 ms

Can be parameterised (brake parameter run start delay tF)

t4b

= approx. 300 ms

Time for determination of commutator position

Fig.

7.1 Timing diagram switch-on sequence