10 installation and commissioning examples, 1 example using dhcp ip address assignment, 1 mount the modules – HEIDENHAIN MSE 1000 User Manual

Page 111: Installation and commissioning examples

Advertising
background image

Installation and commissioning examples

Example using DHCP IP address assignment

Operating Instructions

111

10

Installation and commissioning examples

Each MSE 1000 system is unique, but the installation and commissioning of most
systems is similiar.

Install the MSE 1000 system

Configure the MSEsetup software

Configure the network communication settings

Setup the modules

Setup the encoders

10.1

Example using DHCP IP address assignment

The following information provides an example for how to install and commission an
MSE 1000 system with three modules and two encoders using DHCP IP address
assignment.

MSE 1000 modules with encoders:

MSE 1201 (ID 747501-01) AC 120 V power supply module

MSE 1184 (ID 747500-01) 1 V

PP

base module with one ST 128x length gauge

MSE 1314 (ID 747503-01) 4-channel EnDat module with one AT 1217 length gauge

10.1.1

Mount the modules

Mount power supply
module

Mount the MSE 1201 (ID 747501-01) power supply module. Refer to "Mounting a
module", page 19.

Mount base module

Mount the MSE 1184 (ID 747500-01) 1 V

PP

base module. Refer to "Mounting a

module", page 19.

Connect power supply
and base module

Connect the power supply module and the base module. Refer to "Connecting
modules", page 20.

Mount EnDat module

Mount the MSE 1314 (ID 747503-01) 4-channel EnDat module. Refer to "Mounting a
module", page 19.

Connect base and
EnDat module

Connect the base module and the 4-channel EnDat module. Refer to "Connecting
modules", page 20.