10 installation and commissioning examples, 1 example using dhcp ip address assignment, 1 mount the modules – HEIDENHAIN MSE 1000 User Manual
Page 111: Installation and commissioning examples

Installation and commissioning examples
Example using DHCP IP address assignment
Operating Instructions
111
10
Installation and commissioning examples
Each MSE 1000 system is unique, but the installation and commissioning of most
systems is similiar.
Install the MSE 1000 system
Configure the MSEsetup software
Configure the network communication settings
Setup the modules
Setup the encoders
10.1
Example using DHCP IP address assignment
The following information provides an example for how to install and commission an
MSE 1000 system with three modules and two encoders using DHCP IP address
assignment.
MSE 1000 modules with encoders:
MSE 1201 (ID 747501-01) AC 120 V power supply module
MSE 1184 (ID 747500-01) 1 V
PP
base module with one ST 128x length gauge
MSE 1314 (ID 747503-01) 4-channel EnDat module with one AT 1217 length gauge
10.1.1
Mount the modules
Mount power supply
module
Mount the MSE 1201 (ID 747501-01) power supply module. Refer to "Mounting a
module", page 19.
Mount base module
Mount the MSE 1184 (ID 747500-01) 1 V
PP
base module. Refer to "Mounting a
Connect power supply
and base module
Connect the power supply module and the base module. Refer to "Connecting
modules", page 20.
Mount EnDat module
Mount the MSE 1314 (ID 747503-01) 4-channel EnDat module. Refer to "Mounting a
module", page 19.
Connect base and
EnDat module
Connect the base module and the 4-channel EnDat module. Refer to "Connecting