Installation Guide for Galaxy Power Systems
Issue 12 August 2012
Converters 9 - 5
Converter Wiring
Refer to Figures 9-4, 9-5, and 9-6 for the following procedure.
Converter Wiring
Step
Action
1
Connect the system ground reference wire from the
distribution to the return bus bar in the cabinet. (See Figures
9-4 and 9-5.)
2
For 597A converter carrier only, install the required number
of load circuit breakers, leaving them in the OFF position.
(See Figure 9-6.)
For 597B converter carrier, do not install the fuses at this
time. See Section 15.
3
Connect the 48V load and return wires from the converter
carrier to the using equipment. (See Figure 9-4 for converter
carrier connection.)
4
Do not install the converter cards at this time. See Section
15.