Installation Guide for Galaxy Power Systems

Issue 12 August 2012

Thermal Probe and 210E Connections 12 - 9

Connecting a 210E Module to the Controller or BLJ Board,
continued

Connecting a 210E Module to the Controller or BLJ Board

Step

Action

1

Connect the 210E Power Cable Assembly (847925435 or 848341632) to the ABS and
DG terminals of the BLJ Terminal Board. See Figure 12-7 (BLJ) or 12-8 (Millennium).

2

Connect the Alarm and Signal Cable Assembly to the BLJ board using cable assembly
848302048 (see Figure 12-7) or 848153003 to the BSH board on the Millennium (see
Figure 12-8).

Note: The length of the 848302048 cable assembly is 8 feet (2.4 meters). The cable
assembly can be cut to a shorter length if mounting the 210E module on the bay door.

Figure 12-7: 210E Connection to Vector Controller or BLJ