Installation Guide for Galaxy Power Systems

Issue 12 August 2012

Power Up and Installation Completion 15 - 5

Initial Power Up of the System, continued

Initial Power Up of the System

Step

Action

Install First

Rectifier

2

Install a rectifier in slot one. See Figures 15-3 and 15-4.

Caution

Rectifier is heavy (up to 75 lbs.)

a. Verify that rectifier matches the ac input voltage of the system.

Caution

DO NOT INSTALL 595B OR 595LTB RECTIFIERS INTO

380/400/480Vac systems; they will will be damaged.

b. Verify that the control switch on the front of the rectifier is in the

standby (STBY) position; for 595 rectifiers, verify that the output
circuit breaker is also OFF.


When installing a 595LTA or 595LTB rectifier into a single
rectifier shelf, remove the Rear Keying Plate and install the
Keying Bracket onto the rectifier. See Figure 15-4.

1. Remove Rectifier Rear Keying Plate by removing 2 securing

screws. Save Rear Keying Plate for future re-use. See note
below.

2. Replace the two Rectifier Rear Keying Plate screws onto

rectifier and torque to 10 in-lb (1.1 Nm).

3. Remove Screw "A".
4. Install Keying Bracket using Screw "A" removed in Step 3, and

2 additional screws supplied with the keying bracket. Torque to
10 in-lb (1.1 Nm).

5. Move keying pin on keying bracket to 480Vac position if

rectifier is 595LTA.

Note: Rectifier is not keyed in dual rectifier shelf with Rear
Keying Plate removed.

Continued on next page.