Connecting Thermal Probe Cable Assembly

Millennium

Controller

This procedure is for connecting thermal probe cable assemblies to the
BLJ board and/or Millennium controller.

Note: To enable slope thermal compensation in a basic-only Millennium
controller or to enable enhanced reserve time prediction in an intelligent
Millennium controller, cable B, C, or H must be connected to the
Millennium P3 UBT port.

Connect probes according to one of the options shown in Figure 12-1.

Note: Refer to Table 12-A for alpha designations in Figure 12-1.

Figure 12-1: Thermal Probe Cable Assembly Connection