Cabinet Ground

Procedure

The next step is to ground the cabinet framework. Local grounding
practices will determine the grounding method and the size of cable
connected to the cabinet. A 2-gauge pigtail (847992070), as shown in
Figures 5-13 and 5-14, is provided for this purpose.

Cabinet Ground

Step

Action

1

Run and connect the framework ground lead as shown in
Figure 5-13 or 5-14.

2

Torque connection as specified in Figure 5-13 or 5-14.

Central Office

Ground Procedure

The system ground should be connected to the building’s principal
ground point (Central Office Ground). The conductor size must conform
to local standards.

Centralized Architecture

Follow local practice for Centralized Architecture.

Distributed Architecture

Connection to the power system is through the M10 studs located on the
distribution return bus. See Figure 5-13 (full-height cabinet) or 5-14
(half-height cabinet).

Central Office Ground for Distributed Architecture

Step

Action

1

Run and connect the system ground lead to the initial
cabinet return bus. This connection will connect the return
side of the dc system to earth ground.

2

Torque connections as specified in Figure 5-13 or 5-14.