Initial System Checkout and Preparation for Power Up
Before Installing
Converters and
Rectifiers
Prior to installing converters (if equipped) and rectifiers, verify that the
correct ac voltage is present at the ac connectors in the rectifier shelves.
Note: Disregard if this was done as part of the “AC Connection and
Wiring” procedure.
Safety Reminder
Some of the following procedures are performed while ac voltage is
present at the cabinet; exercise extreme caution and observe all
precautions described in the safety section of this product manual.
Controller Front Panels
Illustrations
Refer to the following figures for illustrations of the controller front
panels:
Figures 15-1a and 15-1b Millennium Controller
Figures 15-2a and 15-2b Vector Controller