Testing rectifiers and load share – GE Industrial Solutions Galaxy Power Systems User Manual
Page 205
Advertising
Installation Guide for Galaxy Power Systems
Issue 12 August 2012
Power Up and Installation Completion 15 - 21
Testing Rectifiers and Load Share
Testing Rectifiers and Load Share
Step
Action
1
Turn all rectifiers to STBY.
2
Connect a resistive load box (proper voltage) to the system’s
positive and negative bus bars.
3
Verify that the system load is less than 50 amperes.
4
Increase the system load to 50 amperes.
5
Turn ON all the rectifiers; after approximately 60 seconds,
verify that the load is divided equally among all the rectifiers
(within 2 amperes).
6
Reduce the system load. Verify that the rectifiers continue to
share the load.
7
Remove system load.