12.

Observe the following messages appear sequentially on the PPU status line:

WAITING FOR INPUT

DC STARTING

INVERTER STARTING

SYNCING

ONLINE

The rectifier and inverter turn on. When the inverter reaches full voltage, UPS output

contactor K3 closes and the static switch turns off supplying power to the critical load

in Normal mode. It takes less than 1 minute for the UPS to achieve Normal mode.

13.

The UPS is now operating in the Normal mode and the

NORMAL status

indicator is illuminated.

9.3

Starting the UPS in Bypass Mode

If the Inverter Output of the UPS is not available and the critical load needs to be

energized, perform the following procedure:

1.

Ensure the UPS circuit breakers and switches are set as follows:

UPS Input Breaker (CB1)

OPEN

UPS Battery Breaker (CB2)

OPEN

UPS Maintenance Bypass Switch

UPS

Options Cabinet Maintenance Bypass Switch (if installed)

UPS

2.

Close the UPS input feeder circuit breaker.

3.

If UPS is dual feed, close UPS Bypass input feeder circuit breaker.

4.

If Options cabinet is installed, close Options cabinet Input, Bypass, and Output

circuit breakers.

5.

Observe UPS monitor screen becoming active as an indication of logic power.

6.

Press the System Control pushbutton. The System Control screen appears.

7.

On the System Control screen, the PPU status should indicate SHUTDOWN,

after approximately 20 seconds

8.

Select

BYPASS from the System Control menu.

Bypass Mode Requested appears on the screen.

The critical load is immediately supplied by the bypass source, in Bypass mode.

9.

The UPS is now operating in the bypass mode and the

BYPASS status

indicator is illuminated.