NOTE: Remove Options cabinet PDM conduit landing plate to punch conduit holes.

15.

Install Square-D Type QO or QOB breakers into PDM panelboard. Refer to

Appendix A of this manual for access information.

16.

Wire branch circuits in accordance with branch circuit breaker manufacturers

instructions (output from the UPS or Options cabinet is prewired to the PDM).

Refer to Appendix A of this manual wiring access information.

17.

After wiring the Options cabinet to the facility power and critical load, be sure

to ground the system according to local and/or national electrical wiring codes.

18.

When all wiring is complete, connect battery strings in accordance with

instructions contained in paragraphs 3.4.1 and 3.4.2 of Chapter 3.

19.

Secure the UPS by reinstalling safety shield panels, front vented panels, and

front solid panel.

20.

Install side panel removed from the UPS cabinet to the left side of the Options

cabinet.

21.

Secure the Options cabinet by reinstalling front vented panel.

2.5

Initial Startup

Startup and operational checks should be performed only by authorized service

personnel. Contact service in advance (usually a two week notice is required) to

reserve a preferred startup date.

2.6

Completing the Installation Checklist

The final step in installing your UPS system is completing the following Installation

Checklist. This checklist ensures that you have completely installed all hardware,

cables, and other equipment. Completing all items listed on the checklist will

ensure a smooth installation. You should make a copy of the Installation Checklist

before filling it out, and retain the original.
After your installation is complete, a service representative will be able to verify the

operation of your UPS system and commission it to support your critical load. The

service representative cannot perform any installation tasks other than verifying

software and operating setup parameters. Service personnel may request a copy

of the completed Installation Checklist to be sure you have completed all

applicable equipment installation.

NOTE: The Installation Checklist MUST be completed prior to starting the UPS

system for the first time.