Battery Cabinet Installation

To install optional battery cabinets, perform the procedures in the following

paragraphs.

2.3.1

Unloading the Battery Cabinet from the Pallet

To remove the Battery cabinet from the pallet, refer to paragraph 2.2.1.

2.3.2

Joining the Battery Cabinet to the UPS Cabinet

To join battery cabinets to the UPS, perform the following steps. Refer to

Figure 2---5 for non-permanent installation or Figure 2---6 for permanent installation

of the Powerware 9330 (10 kVA---20 kVA) UPS and Figure 2---7 for non-permanent

installation or Figure 2---8 for permanent installation of the Powerware 9330

(25 kVA---40 kVA) UPS.

1.

Roll the Battery cabinet to a spot near the right side of the UPS.

2.

Remove left front solid panel, and right front vented panel from the Powerware

9330 (10 kVA---20 kVA) UPS cabinet or left front solid panel and front vented

panels from Powerware 9330 (25 kVA---40 kVA) UPS cabinet. Front panels are

secured with magnetic latches and are removed by pulling panels straight

forward to disengage magnetic latches (see Figure 2---1 or 2---3).

3.

Remove front vented panel from Battery cabinet. The front panel is secured

with magnetic latches and are removed by pulling panels straight forward to

disengage magnetic latches.

4.

Remove right side outside panel from UPS cabinet. Retain hardware.

5.

Remove right side panel from Battery cabinet. Retain hardware.

6.

Install side panel removed from the Battery cabinet to the right side of the UPS

cabinet. Secure with screws removed from UPS cabinet.

7.

Find the battery cable with 2-pole connector in the Battery cabinet. Route this

connector into the UPS cabinet and mate with the matching connector in the

UPS (see Figures 2---5, 2---6, 2---7, or 2---8).

8.

Push the Battery cabinet against the right side of the UPS cabinet.

9.

If permanently mounting the system, proceed to step 16; otherwise, proceed to

step 10.

10.

Secure the Battery cabinet in position by lowering the leveling feet, until

cabinet is not resting on the casters and the cabinet is level.

11.

Secure the front of Battery cabinet to the front of the UPS cabinet by sliding the

angle grounding/mounting bracket, from installation kit, behind the base of the

Battery and UPS cabinets with the bottom angle facing outward (see Figures

2---5 or 2---7). Use hardware provided in the kit to secure the bracket.

12.

Remove the top side panel mounting screw (tie/grounding bracket location in

Figures 2---5 or 2---7) from both the Battery and UPS cabinets.

13.

Secure the back of Battery cabinet to the back of the UPS cabinet with the

tie/grounding bracket. Secure the bracket with the side panel mounting

screws.