1 installation checklist – Powerware 9330 User Manual
Page 55

2--29
Powerware 9330 (10 kVA--40 kVA) Installation and Operation
164201300 REV. G 061502
2.6.1
Installation Checklist
-
All packing materials and restraints have been removed from each cabinet.
-
Each cabinet in the UPS system is placed in its installed location.
-
A cabinet grounding/mounting kit is installed between any cabinets that are bolted
together.
-
All conduits, and cables are properly routed to the UPS and auxiliary cabinets.
-
All power cables are properly sized and terminated.
-
The bypass source of the supply is a four wire wye configuration. If using dual feed, the
rectifier source is a three wire connection from a wye configuration.
-
All telephone and network connections have been completed.
-
A ground conductor is properly installed.
-
Internal battery cabinet connections have been completed (plugs, etc.).
-
Air conditioning equipment is installed and operating correctly.
-
The area around the installed UPS system is clean and dust-free. (It is recommended
that the UPS be installed on a level floor suitable for computer or electronic
equipment.)
-
Adequate workspace exists around the UPS and other cabinets.
-
Adequate lighting is provided around all UPS equipment.
-
A 120V service outlet is located within 25 feet of the UPS equipment.
-
The Remote Emergency Power Off (EPO) device is mounted in its installed location
and its wiring terminated inside the UPS cabinet.
-
Summary alarms and/or building alarms are wired appropriately. (OPTIONAL)
-
Startup and operational checks performed by authorized service personnel.