This section describes the following installation sequence for the CPS6000-M2 power system.

1. Preparations
2. Anchoring

frame

3.

Connecting frame ground

4.

Connecting CO ground

5.

Connecting ac utility

6. Installing

batteries

7.

Wiring dc loads and installing fuses/circuit breakers

8.

Installing rectifiers and converters

9.

Controller Connections

10.

Starting Up System

Preparation

Safety

Please review all safety warnings in Section 3 before beginning the installation process. Observe
all warnings and labels on the equipment.

WARNING: Due to the possibility of working on energized circuits during these
procedures, all tools and test equipment must be insulated in an approved manner.
Proper ESD protection is required in order to prevent ESD damage to the
equipment.

WARNING: Only qualified personnel should install and service the power
system and plug-in modules. Hazardous energy and voltages are present in the
unit and on the interface cables and will shock or cause serious injury or death if
safety precautions are ignored. Follow all safety warnings and practices when
servicing this equipment.