Installing and wiring dc loads – GE Industrial Solutions CPS6000-M2 User Manual

Page 40

Advertising
background image

CPS6000-M2 Installation Guide H5694720

Issue 8 January 2008

40

Installing and Wiring DC Loads

Installing DC Bullet Style Distribution

Bullet Terminal distribution panels accept Bullet Terminal Circuit Breakers, TPS Fuse Holders,
and GMT Fuse Modules.

CAUTION: Ensure Circuit Breakers are in the OFF position prior to installation. Ensure
Fuse Holders are empty prior to installation.

CAUTION: In order to meet UL Listing temperature limits, GMT Fuses on the bullet fuse

module must meet these layout restrictions:

• All 12A rated fuses must have an unused position to at least one side.
• All 15A rated fuses must not be installed next to another fuse. Leave empty position.

CAUTION: In order to meet UL Listing temperature limits, bullet distribution panels

must meet the following layout restrictions

• Panel is rated 400A but derates to 350A if Large Breakers or Fuses are installed in the

Center Section of distribution.

• bullet circuit breakers rated 80A, 90A and 100A require one adjacent position be left

unoccupied.

Step

Action

1

Loosen screws and swing hinged retainer cover clear of the distribution devices (if
present).

Vertical distribution panel

2

Insert distribution devices into the panel load busses as shown in the figure above.

3

Connect loads.

Note: To allow for future growth start from the top most position and work down the
panel. This will allow orderly and managed cable dressing as loads are added.