SAS Link and Transport Layer Test Suite v0.13

Test 7.1.3 - Link Reset – HARD_RESET Received

Purpose: To determine that the DUT properly handles a received HARD_RESET.

References:

7.2.5.8, 7.9.1 SAS Standard

Resource Requirements: SAS Protocol Analyzer and Generator

Revision History: September 7, 2004

Test Setup: The DUT and the Testing Station are physically connected.


Test Procedure:

• The Testing Station should transmit COMINT to start a Phy Reset sequence with the DUT.

• The Testing Station should complete a Phy Reset sequence with the DUT.

• Once the Phy reset sequence between the DUT and the Testing Station are complete, the Testing

Station should transmit 6 consecutive HARD_RESET primitives. This must occur before the Identify
sequence is complete.

Observable Results:

• Verify that the DUT transmits COMINIT upon receiving the HARD_RESET primitives from the

Testing Station.