SAS Link and Transport Layer Test Suite v0.13

Test 7.4.6 - Closing SSP Connections – BREAK Sourced by DUT

Purpose: To determine that the DUT properly sources BREAK when required.

References:

7.12.7 SAS Standard

Resource Requirements: SAS Protocol Analyzer and Generator

Revision History: September 13, 2004

Test Setup: The DUT and the Testing Station are physically connected.

Test Procedure (Targets):

• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence

with the DUT. Since the DUT is a target the Testing Station should transmit an Identify Address frame
indicating that it is an initiator.

• The Testing Station should open an SSP connection to the DUT.

• Wait for the DUT to transmit OPEN_ACCEPT and RRDY. The Testing Station should transmit a

SCSI INQUIRY command to the DUT, then close the connection.

• Wait for the DUT to open an SSP connection to the Testing Station. Allow the DUT to transmit a SCSI

Response to the Testing Station.

• When the DUT transmits CLOSE (NORMAL) to close the connection, the Testing Station should not

transmit CLOSE (NORMAL) in response.


Observable Results: Verify that the DUT transmitted BREAK within 1 msec of transmitting CLOSE (NORMAL)
to the Testing Station.