SAS Link and Transport Layer Test Suite v0.13

Test 9.6.4 - SSP ERROR HANDLING – Extra RESPONSE frame Received

Purpose: To determine that the DUT, an SSP Initiator port, responds properly when a RESPONSE frame is
improperly retransmitted.

References:

9.2.4.5 SAS Standard

Resource Requirements: SAS Protocol Analyzer and Generator.

Revision History: September 28, 2004

Test Setup: The DUT and the Testing Station are physically connected.

Test Procedure (SSP Initiator):

• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence

with the DUT. Since the DUT is an initiator the Testing Station should transmit an Identify Address
frame indicating that it is a SAS Target.

• Allow the DUT to open an SSP connection to the Testing Station and transmit a SCSI INQUIRY

command.

• The Testing Station should open a connection to the DUT and transmit DATA and 2 RESPONSE

frames to the DUT. The second response frame should have the retransmit bit set to 1. Close the
connection.


Observable Results: Verify that if the DUT discards the second RESPONSE frame and does not transmit ACK or
NAK in response to it.