Teledyne LeCroy SAS Verification Test Descriptions User Manual

Page 181

Advertising
background image

University of New Hampshire

InterOperability Laboratory

expected to do the same.

11. The Testing Station is the instructed to transmit its Phy Capabilities bits indicating

support for all speeds. The Testing Station is instructed to indicate that it does not
support 6.0 Gbps signaling without SSC. The DUT is expected to transmit it's Phy
Capabilities Bits.

12. The Testing Station is instructed to transmit D.C. Idle for one RCDT. The DUT is

expected to do the same.

13. The Testing Station is instructed to then transmit properly formatted TRAIN patterns at

the highest mutually speed. The DUT is expected to do the same.

14. Upon successful reception of a properly formatted TRAIN pattern from the DUT, the

testing station is instructed to transmit a properly formatted TRAIN_DONE pattern to
the DUT for the remainder MTT. The DUT is expected to do the same upon successful
reception of a TRAIN pattern from the testing station.

Observable Results

Verify that the DUT transmits at least one TRAIN pattern and at least four
TRAIN_DONE patterns at 6G with SSC before MTT has expired.

Possible Problems

Lower level testing will have to be used to verify that the DUT enabled SSC properly.

UNH-IOL

SAS 2.0 Speed Negotiation

45 of 49

Advertising