Teledyne LeCroy SAS Verification Test Descriptions User Manual
Page 82
The University of New Hampshire
InterOperability Laboratory
Serial Attached SCSI Consortium
81
SAS Link and Transport Layer Test Suite v0.13
Test 7.4.4 - Closing SSP Connections – CLOSE (NORMAL)
Purpose: To determine that the DUT properly responds when CLOSE (NORMAL) is received.
References:
7.16.6, 7.12.7 SAS Standard
Resource Requirements: SAS Protocol Analyzer and Generator
Revision History: September 13, 2004
Test Setup: The DUT and the Testing Station are physically connected.
Test Procedure (Initiators):
• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence
with the DUT. Since the DUT is an initiator the Testing Station should transmit an Identify Address
frame indicating that it is a target.
• Wait for the DUT to open an SSP connection to the Testing Station. Allow the DUT to transmit a SCSI
Command to the Testing Station, then close the connection.
• The Testing Station should transmit an OpenAddress frame to the DUT. Wait for OPEN_ACCEPT
from the DUT, then transmit CLOSE (NORMAL)
Observable Results: Verify that the DUT transmitted CLOSE (NORMAL) within 1 msec of receiving CLOSE
(NORMAL) from the Testing Station.