SAS Link and Transport Layer Test Suite v0.13

Test 7.2.1 - Connections – OPEN_ACCEPT

Purpose: To determine that the DUT properly transmits RRDY after receiving OPEN_ACCEPT.

References:

7.12.2.2 SAS Standard

Resource Requirements: SAS Protocol Analyzer and Generator

Revision History: September 7, 2004

Test Setup: The DUT and the Testing Station are physically connected.

Test Procedure (Targets):

• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence

with the DUT. Since the DUT is a target the Testing Station should transmit an Identify Address frame
indicating that it is an initiator.

• The Testing Station should transmit an Open Address frame to the DUT. Wait for the DUT to transmit

OPEN_ACCEPT and RRDY.



Observable Results:

• Verify that the DUT transmitted RRDY no more than 1 ms after transmitted OPEN_ACCEPT.