Teledyne LeCroy SAS Verification Test Descriptions User Manual
Page 114
The University of New Hampshire
InterOperability Laboratory
Serial Attached SCSI Consortium
113
SAS Link and Transport Layer Test Suite v0.13
Test 7.5.6.1 - AIP –Transmitted
Purpose: To determine that the DUT, a SAS Expander properly transmits AIP
References:
7.12.2.2, 7.12.5.1 SAS Standard
Resource Requirements: SAS Protocol Analyzer and Generator. SAS Target.
Revision History: September 13, 2004
Test Setup: The DUT and the Testing Station are physically connected. The DUT is physically connected to a SAS
Target.
Test Procedure (SAS Expander):
• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence
with the DUT. Since the DUT is an expander with an attached target the Testing Station should
transmit an Identify Address frame indicating that it is an initiator.
• The Testing Station should open an SMP Connection to the DUT an transmit a REPORT_GENERAL
SMP Request. The DUT should transmit a REPORT_GENERAL SMP Response.
• The Testing Station should open an SMP Connection to the DUT and transmit a DISCOVER SMP
Request to the DUT Phy which is attached to the SAS Target. The DUT should transmit a DISCOVER
SMP Response with this information.
• The Testing Station should transmit an OpenAddress frame for an SSP Connection to the SAS Target
attached to the DUT.
Observable Results: Verify that the DUT transmits AIP to the Testing Station upon receiving the connection
request. The AIP must be transmitted within 128 dwords of the Open, and AIP must be sent at least every 128
dwords until the connection is established from the DUT to the attached SAS Target.