SAS Link and Transport Layer Test Suite v0.13

Test 7.4.5 - Closing SSP Connections – BREAK Sourced by Testing Station

Purpose: To determine that the DUT properly responds when BREAK is received.

References:

7.12.6 SAS Standard

Resource Requirements: SAS Protocol Analyzer and Generator

Revision History: September 13, 2004

Test Setup: The DUT and the Testing Station are physically connected.

Test Procedure (Targets):

• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence

with the DUT. Since the DUT is a target the Testing Station should transmit an Identify Address frame
indicating that it is an initiator.

• The Testing Station should transmit an OpenAddress frame to the DUT, followed by BREAK.


Observable Results: Verify that the DUT transmitted BREAK within 1 msec of receiving BREAK from the
Testing Station.