SAS Link and Transport Layer Test Suite v0.13
Test 7.4.5 - Closing SSP Connections – BREAK Sourced by Testing Station
Purpose: To determine that the DUT properly responds when BREAK is received.
References:
7.12.6 SAS Standard
Resource Requirements: SAS Protocol Analyzer and Generator
Revision History: September 13, 2004
Test Setup: The DUT and the Testing Station are physically connected.
Test Procedure (Targets):
• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence
with the DUT. Since the DUT is a target the Testing Station should transmit an Identify Address frame
indicating that it is an initiator.
• The Testing Station should transmit an OpenAddress frame to the DUT, followed by BREAK.
Observable Results: Verify that the DUT transmitted BREAK within 1 msec of receiving BREAK from the
Testing Station.