Teledyne LeCroy SAS Verification Test Descriptions User Manual

Page 26

Advertising
background image

The University of New Hampshire

InterOperability Laboratory



Serial Attached SCSI Consortium

25

SAS Link and Transport Layer Test Suite v0.13

Test 7.4.2 - Closing SSP Connections – DONE (ACK/NAK TIMEOUT)

Purpose: To determine that the DUT properly responds when ACK or NAK has not been received for a transmitted
frame.

References:

7.16.6 SAS Standard

Resource Requirements: SAS Protocol Analyzer and Generator

Revision History: September 13, 2004

Test Setup: The DUT and the Testing Station are physically connected.

Test Procedure (Targets):

• The Testing Station should start and complete a Phy Reset sequence followed by an Identify sequence

with the DUT. Since the DUT is a target the Testing Station should transmit an Identify Address frame
indicating that it is an initiator.

• The Testing Station should open an SSP connection to the Testing Station.

• Wait for the DUT to transmit OPEN_ACCEPT and RRDY. The Testing Station should transmit a

SCSI INQUIRY command to the DUT, then close the connection.

• Wait for the DUT to open an SSP Connection to the Testing Station. Allow the DUT to transmit a

SCSI Response. The Testing Station should not transmit ACK or NAK.


Observable Results: Verify that the DUT transmitted DONE (ACK/NAK TIMEOUT) within 1 msec of
transmitting the Command or Response frame.

Advertising