Commissioning

Preparing the commissioning procedure

8

l

141

EDS84DPS424 EN 5.0

Notes on commissioning in the case of an external 24 V supply

The following sequence must be observed when commissioning devices with an external
24 V supply:

ƒ

Switch−on
– Connection of the external 24 V supply

The control electronics and fieldbus communication are started and the display
shows the "LU" message (undervoltage in the DC bus)

– Connection of the 400 V mains voltage

The message in the display goes off / changes over to .

ƒ

Switch−off
– Switch−off of the 400 V mains voltage
– Switch−off of the 24 V supply

)

Note!

The functions of the control electronics become inactive when the 24 V supply
is switched off. The switch function of Ethernet−based fieldbuses is also
inactive.
Switching the 24 V supply when the mains voltage is applied may lead to an
error status in higher−level controls.

Notes for the commissioning of EMS versions

For EMS version devices, in addition the following has to be observed:

ƒ

Devices with a rocker switch control element
– To enable the controller, the rocker switch has to be operated.
– Operating the rocker switch again inhibits the controller.

ƒ

Device without a rocker switch control element
The controller has to be enabled using the available communication options.