Operation, 1 preparation for operation, Operation -1 – Yokogawa GD40 Gas Density Detector User Manual

Page 44: Preparation for operation -1 3.1.1

Advertising
background image

<3. Operation>

3-1

IM 11T3E1-01E

3.

OPERATION

This chapter explains how to operate the GD402 Analyzers.

3.1

Preparation for Operation

CAUTION

(1) DO NOT supply power to the analyzer when inspecting it.
(2) Leave the power switch which is built in the converter, in the ON position.
(3) DO NOT open the terminal box cover with the power turned on, if the analyzer is installed in

an explosion-hazardous area.

(4) When using the converter under high ambient temperatures, be careful as the metal parts of

the converter will also be hot.

3.1.1

Inspecting Installation, Piping and Wiring

Workmanship

Before turning the power on, inspect workmanship with regards to installation, piping and wiring

as instructed below:

l

Examine how the GD402 analyzer and its peripheral equipment are installed.

l

Check the sample-gas line, which feeds the GD40 detector, for any gas leakage.

l

Inspect the system to ensure that the GD402 analyzer and its peripheral equipment are

wired correctly. After inspection, shut the terminal box cover securely.

l

Place the power switch built in the GD402T, GD402V, GD402R converter (explosion-

protected) in the ON position.

Advertising
This manual is related to the following products: