Please note while programming – HEIDENHAIN iTNC 530 (340 49x-05) Cycle programming User Manual

Page 152

Advertising
background image

152

Canned Cycles: Pocket Milling / Stud Milling / Slot Milling

5.5 CIR

C

ULAR SL

O

T

(Cy

c

le 254, DIN/ISO: G254)

Please note while programming:

With an inactive tool table you must always plunge
vertically (Q366=0) because you cannot define a plunging
angle.

Pre-position the tool in the machining plane with radius
compensation R0. Define Parameter Q367 (Reference for
slot position)

appropriately.

The TNC runs the cycle in the axes (machining plane) with
which you approached the starting position. For example,
in X and Y if you programmed CYCL CALL POS X... Y... or
in U and V if you programmed CYCL CALL POS U... V...

The TNC automatically pre-positions the tool in the tool
axis. Note Parameter Q204 (2nd setup clearance).

At the end of the cycle the TNC returns the tool to the
starting point (center of the circular arc) in the working
plane. Exception: if you define a slot position not equal to
0, then the TNC only positions the tool in the tool axis to
the 2nd setup clearance. In these cases, always program
absolute traverse movements after the cycle call.

The algebraic sign for the cycle parameter DEPTH
determines the working direction. If you program
DEPTH = 0, the cycle will not be executed.

If the slot width is greater than twice the tool diameter, the
TNC roughs the slot correspondingly from inside out. You
can therefore mill any slots with small tools, too.

The slot position 0 is not allowed if you use Cycle 254
Circular Slot in combination with Cycle 221.

Danger of collision!

Enter in MP7441 bit 2 whether the TNC should output an
error message (bit 2=1) or not (bit 2=0) if a positive depth
is entered.

Keep in mind that the TNC reverses the calculation for pre-
positioning when a positive depth is entered. This
means that the tool moves at rapid traverse in the tool axis
to setup clearance below the workpiece surface!

If you call the cycle with machining operation 2 (only
finishing), then the TNC positions the tool to the first
plunging depth at rapid traverse: