Installation, 1 piping design precautions, Installation -1 – Yokogawa ADMAG AXR User Manual

Page 13: Piping design precautions -1, 1 piping design precautions warning, Important

Advertising
background image

<3. INSTALLATION>

3-1

IM 01E30D01-01EN

3. INSTALLATION

3.1 Piping Design Precautions

WARNING

Installation of the magnetic flowmeter must

be performed by expert engineer or skilled

personnel. No operator shall be permitted to

perform procedures relating to installation.

IMPORTANT

Design piping correctly, referring to the following

to prevent damage to flowtubes and to assure

accurate measuring.

(1) Location

IMPORTANT

Install the flowmeter in a location where it is

not exposed to direct sunlight. The minimum

ambient temperature is limited by the minimum

fluid temperature of the flowtube. For more

information, refer to Chapter 11 “OUTLINE.” The

flowmeter may be used in an ambient humidity

where the relative humidity ranges from 0 to

100%. However, avoid long-term continuous

operation at relative humidity above 95%.

(2) Noise Avoidance

IMPORTANT

The flowmeter should be installed away from

electrical motors, transformers, inverters

and other power sources in order to avoid

interference with measurement.

(3) Required Lengths of Straight Runs
To maintain accurate measurement, see JIS B7554

“Electro Magnetic Flowmeters” which explains the

requirements for upstream piping conditions of

magnetic flowmeters.
The piping conditions we recommend as shown in

Figure 3.1.1 are based on JIS B7554 and on our

piping condition test data.

When installing two or more magnetic flowmeters

on a single pipe, provide a run of at least 5D

between them.

Gate valve

fully open

Reducer

pipe

5 D or more

2 D or more

2 D or more

2 D or more

10 D or more

10 D or more

5 D or more

5 D or more 0 is allowable

0 is allowable

0 is allowable 0 is allowable

F0301.ai

Tee

90-degree bent

Various valves

Expander

pipe

D: Flowtube Size

Figure 3.1.1 Required Lengths of Straight Runs

*1: Do not install anything in the vicinity that may

interfere with the magnetic field, induced signal

voltages, or flow velocity distributions of the

flowmeter.

*2: A straight run may not be required on the

downstream side of the flowmeter. However,

if a downstream valve or other fitting causes

irregularity or deviation in flows, provide a

straight run of 2D to 3D on the downstream

side.

*3: Highly recommend to mount valves on the

downstream side so that deviated flows do not

occur in the flowtube and to avoid startup from

an empty condition.

(4) Maintaining Stable Fluid Conductivity

IMPORTANT

Do not install the flowmeter where fluid

conductivity tends to become uneven. If

chemicals are fed near the upstream side of a

magnetic flowmeter, they may affect the flow

rate’s indications. To avoid this situation, it is

recommended that the chemical feed ports be

located on the downstream side of the flowmeter.

If it is unavoidable that chemicals must be fed on

the upstream side, provide a sufficient length of

straight run (approximately 50D) to ensure the

proper mixture of fluids.

F0302.EPS

(Incorrect)

Upstream side

(Correct)

Downstream side

Figure 3.1.2 Chemical Injection

Advertising