Features of the Prepared Solution



Prepared Solution Servo PLC / ECSxA 1.1 EN

page 2-14


3. Oversynchronous synchronisation, during this process the master value is measured

by a measuring wheel. The lengths are detected from marks on the material and are
processed.

4. Synchronous synchronisation, during this process the master value is measured by a
measuring wheel. The lengths are detected from marks on the material and are processed.


Can the following physical requirements be taken into account in your application?


You should take into account the following basic design items in your application:

¾

Free travel (distance from initial position – end position) must be sufficient so

that a process sequence can be performed successfully

¾

Maximum cut duration

¾

Maximum velocity of the carriage

¾

Maximum synchronisation velocity

Do you want to process in "parallel" and your process does not require "diagonal"
processing?


During the acceleration to the line speed there is no stopping of the line? (start of flying saw
to hit the synchronous)







?

NO

YES

Your specific application
can be represented via a
modification of the example
solution.
Please contact your Lenze
representative.

?

NO

YES

Your specific application
can be represented via a
modification of the example
solution.
Please contact your Lenze
representative.